Année de construction: 2018
Surface d‘eau:
- Zone de baignade: 33 m²
- Zone de régénération: 10 m²
- Surface totale: 43 m²
Profondeur d‘eau: 1,5 m
Liner: vert
Autre:
Conception et réalisation:
Garten- und Landschaftsbau Kreye GmbH & Co. KG
DE-27777 Ganderkesee